- California levee projects in the works.
- Discussions with a major player in the entrepreneurial and equipment arena for MDM equipment/support.
- Four wind power plants completed in the south of Sweden.
- BKK Water Channel Project is delayed. Then started, and delayed, and so on. At present SpeedTrack is waiting for OK on new design.
- Possibility of manufacturing rigs or sub-assemblies in SEA. Discussions with BKK company.
- Speed Tracks Water Channel project is converted to a MDM project.
- Odensbacken project completed sucessfully, for all involved.
- LCT signs up our first South East Asian licensor and entrepreneur. Speed Track Soilmixing Ltd. has long term soilmixing projects in the pipeline for the next two to three years. Territory for MDM is Thailand.
- Hercules is awarded windpowerplant foundation project for Enercon and Eolusvind AB in Odensbacken, Örebro.
- Gamle Tull is a success! Party pictures on request, only.
- Hercules Grundläggning is awarded the Gamle Tull project utilizing the MDM method. The project started out with a design for CFA columns, but through dedicated and persistant work, MDM was choosen as the foundation construction method. The end result was great money savings for all parties involved and a shorter construction time. For more detailed information contact us.
- MDM is utilized at Rotterdam, Holland, jobsite to finish project.
- Hercules and LCT performs test in Sweden, Torp.
- Hercules signs licensing agreement with LC Technology, Inc.
- Hercules and LCT performs test in Sweden, Tullingge/Bro.
|
|
|